The most a mushroom growing unit draws in Tripura

₹114.75 lakh

The same integrated mushroom unit where the project includes canning, priced at the higher of the two per-tonne norms the clause states.

Paid by NHB Scheme No. 1.

Enhanced rate, NE & Himalayan State, 45%. You reach that only by building all the way to the scheme’s own limit of 300 MT of installed capacity, which the scheme costs at ₹255.00 lakh. A smaller project draws proportionally less.

Your project must be bigger than 50 MT of installed capacity to qualify at all. Below that it pays nothing at all, not simply less.

Type
State
Which rate applies
NE & Himalayan State
Schemes that apply
9
NHB Operational Guidelines, January 2025Printed January 2025Show the clause, the page and our archived copy
Printed in the document as “1 (vi) Integrated Mushroom Production Unit in project mode, with canning”.

National Horticulture Board Operational Guidelines JANUARY 2025 (NHB Operational Guidelines, January 2025)

National Horticulture Board, Ministry of Agriculture & Farmers Welfare, Government of India (Plot No. 85, Sector-18, Institutional Area, Gurugram 122015)

Printed January 2025

Chapter 02, Scheme No. 01, cost norms table, item 1 (vi) (PDF p.17, printed page 7). Item column, verbatim: "Integrated Mushroom Production Unit in project mode". Cost norms column, verbatim: "As per NHB norms for a minimum installed capacity above 50 MT and upto 300 MT in…Read the full clause
Chapter 02, Scheme No. 01, cost norms table, item 1 (vi) (PDF p.17, printed page 7). Item column, verbatim: "Integrated Mushroom Production Unit in project mode". Cost norms column, verbatim: "As per NHB norms for a minimum installed capacity above 50 MT and upto 300 MT in controlled conditions @ Rs. 75000/MT without canning and @ Rs. 85000/ MT with Canning including Production Unit + Compost making Unit." Pattern of assistance column, verbatim: "Credit linked subsidy @ 40% of eligible project cost in General area and @ 50% of eligible project cost for NER and Himalayan States, Scheduled Areas and UTs of Andaman &Nicobar Islands, Lakshadweep Islands, Jammu & Kashmir and Ladakh." Those two percentages were cut to 35% and 45% by NHB's Public Circular of 21 August 2026, cited separately on every rate this record publishes. Read with Chapter 04, Important Instructions, item 16 (PDF p.51, printed page 40), verbatim: "In case of cold storage/CA storage, Mushroom, Ripening chamber, Reefer Van, Cold room and Pre-cooling unit, the EPC is worked out on the basis of capacity." Chapter 01 dates the whole instrument: "The Scheme guidelines shall be effective from 01.01.2025."

PDF p.17 (Chapter 02, item 1(vi)); PDF p.51 (Chapter 04, instruction 16); PDF p.14 (Chapter 01, "Date of Coming into force")

Read on 14 September 2026 by chirag.

The most any one of the 9 schemes that apply here pays for the growing rooms themselves, never a total of them. The growing rooms are not all these schemes fund: see what else they price.

Tripura counts as an NE & Himalayan State, so the central schemes pay a higher share here: 50% of what a scheme assumes an item costs, instead of the usual 40%, on the items that carry the higher rate. Tripura’s own scheme is verified, with 2 rules for mushroom cultivation, below.

See how these schemes actually work for the myths, limits and loopholes behind every figure.

What decides whether you get anything

These are the conditions NHB Scheme No. 1 carries, the scheme behind the figure above. Each of the other schemes on this page carries its own, set out on its own page.

Does this need a bank loan? (credit linked)
Yes. The subsidy rides on a bank loan: a bank sanctions the loan and the subsidy is adjusted against it.
When does the money arrive? (back ended)
After you build, and after an inspection. The subsidy is held in a reserve account and released once the project has been inspected and found complete, not paid up front.
Must it be approved before you start work? (sanction before commencement)
Sanction before commencement applies. The approving authority must issue its sanction before eligible expenditure is incurred. Read what starting work early costs you.

Tripura’s own scheme

TR SHM MIDH Cost Norms (Mushroom)

Directorate of Horticulture & Soil Conservation, Government of Tripura

Verified. Read on 13 September 2026, against the primary government document.

Production Unit

The mushroom growing/production unit itself.

₹8.00 lakh

Private applicant, NE & Himalayan State, 40%.

Tripura State Horticulture Mission MIDH cost norms write-up ("Write up - 1"), Mushrooms componentNo date printedShow evidence

Mission for Integrated Development of Horticulture (MIDH) – A Centrally Sponsored Scheme (Tripura State Horticulture Mission MIDH cost norms write-up ("Write up - 1"), Mushrooms component)

Directorate of Horticulture & Soil Conservation, Government of Tripura (Tripura State Horticulture Mission)

No date is printed on this document.

Table "Cost norms and pattern of assistance under Mission for Integrated Development of Horticulture (MIDH)" (PDF p.5), section "III Mushrooms", sub-items "Production Unit" and "Spawn Making Unit" (the document's own numbering mislabels both "i", not "i"/"ii", reproduced as…Read the full clause
Table "Cost norms and pattern of assistance under Mission for Integrated Development of Horticulture (MIDH)" (PDF p.5), section "III Mushrooms", sub-items "Production Unit" and "Spawn Making Unit" (the document's own numbering mislabels both "i", not "i"/"ii", reproduced as printed).

PDF p.5

Read on 13 September 2026 by chirag.

Spawn Making Unit

The spawn laboratory.

₹6.00 lakh

Private applicant, NE & Himalayan State, 40%.

Same evidence as the rule aboveNo date printedShow evidence

Same evidence as the rule above

Directorate of Horticulture & Soil Conservation, Government of Tripura (Tripura State Horticulture Mission)

No date is printed on this document.

Table "Cost norms and pattern of assistance under Mission for Integrated Development of Horticulture (MIDH)" (PDF p.5), section "III Mushrooms", sub-items "Production Unit" and "Spawn Making Unit" (the document's own numbering mislabels both "i", not "i"/"ii", reproduced as…Read the full clause
Table "Cost norms and pattern of assistance under Mission for Integrated Development of Horticulture (MIDH)" (PDF p.5), section "III Mushrooms", sub-items "Production Unit" and "Spawn Making Unit" (the document's own numbering mislabels both "i", not "i"/"ii", reproduced as printed).

PDF p.5

Read on 13 September 2026 by chirag.

Central schemes that apply in Tripura

These apply everywhere in India; what changes from state to state is the share they pay. Each line shows the most that scheme pays for any one item at Tripura’s rate, and the document it comes from. Between them they also fund a spawn laboratory, a compost yard, a pack house and processing, a cold store, help with loan interest, a credit guarantee and machinery, each at its own rate.

MIDH Operational Guidelines 2025, Annexure V, Item III lists "NE & Himalayan States" among the enhanced-rate areas, defined by its footnote only as "States in North East & Himalayan region covered under HMNEH scheme." That HMNEH enumeration was located at the official HMNEH / TMNEHS scheme portal (Department of Agriculture & Cooperation, Government of India), https://tmnehs.gov.in/, read 11 Sep 2026, archived at content/sources/hmneh-coverage.html (SHA-256 e0193eb29563c36a8c8f69b41299b8f99941e06257a24cea4aa7d68c5d1f9086), which states verbatim: "The mission covers all NE States including Sikkim and three Himalayan states of Jammu & Kashmir, Himachal Pradesh and Uttarakhand." CAVEAT, read before relying on this for a claim: this is a live government page, not an abandoned one, its own footer reads "Last Updated On :17/10/2019" (17 October 2019, verified directly against the archived file), roughly two years after its "What's New" bulletins end (which run only through 2017-18; an earlier version of this note wrongly read that gap, plus the page's boilerplate "© 2010" copyright line, as the whole page being frozen and untouched since, the copyright year is a static template value on this class of government site and does not track content updates). That October 2019 update is still before the Jammu & Kashmir Reorganisation Act, 2019 took effect (31 October 2019, the "appointed day" that split the erstwhile state into the Union Territories of Jammu & Kashmir and Ladakh), and the page's own text still reads "Jammu & Kashmir" as the pre-2019 undivided state, so it still does not speak to how J&K (UT) and Ladakh (UT) are separately treated today, just not because the page was abandoned. See LADAKH_NOTE for how that gap is handled for Ladakh.
  • MIDH₹300.00 lakh

    At most, for its biggest single item: The same Cold Storage Type-I, built instead as a pre-engineered building (PEB) frame combined with civil work and PUF/PIR panels, priced per tonne of storage capacity up to 5,000 MT, at a higher per-MT rate than the plain-civil row.

    Enhanced rate, NE & Himalayan State, 50%.

    MIDH Operational Guidelines 2025Printed 31 December 2024Show evidence

    OPERATIONAL GUIDELINES MISSION FOR INTEGRATED DEVELOPMET OF HORTICULTURE (MIDH Operational Guidelines 2025)

    Department of Agriculture & Farmers Welfare, Government of India (published on nhb.gov.in)

    Printed 31 December 2024

    Annexure V, Item C.7 "Cold Storage Type-I (CS-1)", row (ii), verbatim: "Cold Storage Type-I is defined as CS-1 with Construction in combination of civil & PEB including PUF/PIR panels, Doors and Ante-rooms, Refrigeration Units, Electrical Installation, Administrative block,…Read the full clause
    Annexure V, Item C.7 "Cold Storage Type-I (CS-1)", row (ii), verbatim: "Cold Storage Type-I is defined as CS-1 with Construction in combination of civil & PEB including PUF/PIR panels, Doors and Ante-rooms, Refrigeration Units, Electrical Installation, Administrative block, Safety/Fire Safety and Hazard control and basic mezzanine structure." Cost Norms column, verbatim: "Rs. 12000/MT, (Max 5,000 MT capacity)." Pattern of Assistance column, verbatim: "Credit linked back-ended assistance @ 35% in General areas and 50% in the case of NE & Himalayan States, Scheduled areas, vibrant villages, Andaman & Nicobar and Lakshadweep Islands." plus "Note: Component has to be implemented in accordance to NCCD guidelines only."

    PDF p.66

    Read on 11 September 2026 by chirag.

    Verified against the primary government document.

    See all 8 items MIDH prices
  • NHB Scheme No. 1₹114.75 lakh

    At most, for its biggest single item: The same integrated mushroom unit where the project includes canning, priced at the higher of the two per-tonne norms the clause states.

    Enhanced rate, NE & Himalayan State, 45%.

    NHB Operational Guidelines, January 2025Printed January 2025Show evidence

    National Horticulture Board Operational Guidelines JANUARY 2025 (NHB Operational Guidelines, January 2025)

    National Horticulture Board, Ministry of Agriculture & Farmers Welfare, Government of India (Plot No. 85, Sector-18, Institutional Area, Gurugram 122015)

    Printed January 2025

    Chapter 02, Scheme No. 01, cost norms table, item 1 (vi) (PDF p.17, printed page 7). Item column, verbatim: "Integrated Mushroom Production Unit in project mode". Cost norms column, verbatim: "As per NHB norms for a minimum installed capacity above 50 MT and upto 300 MT in…Read the full clause
    Chapter 02, Scheme No. 01, cost norms table, item 1 (vi) (PDF p.17, printed page 7). Item column, verbatim: "Integrated Mushroom Production Unit in project mode". Cost norms column, verbatim: "As per NHB norms for a minimum installed capacity above 50 MT and upto 300 MT in controlled conditions @ Rs. 75000/MT without canning and @ Rs. 85000/ MT with Canning including Production Unit + Compost making Unit." Pattern of assistance column, verbatim: "Credit linked subsidy @ 40% of eligible project cost in General area and @ 50% of eligible project cost for NER and Himalayan States, Scheduled Areas and UTs of Andaman &Nicobar Islands, Lakshadweep Islands, Jammu & Kashmir and Ladakh." Those two percentages were cut to 35% and 45% by NHB's Public Circular of 21 August 2026, cited separately on every rate this record publishes. Read with Chapter 04, Important Instructions, item 16 (PDF p.51, printed page 40), verbatim: "In case of cold storage/CA storage, Mushroom, Ripening chamber, Reefer Van, Cold room and Pre-cooling unit, the EPC is worked out on the basis of capacity." Chapter 01 dates the whole instrument: "The Scheme guidelines shall be effective from 01.01.2025."

    PDF p.17 (Chapter 02, item 1(vi)); PDF p.51 (Chapter 04, instruction 16); PDF p.14 (Chapter 01, "Date of Coming into force")

    Read on 14 September 2026 by chirag.

    Verified against the primary government document.

    See all 2 items NHB Scheme No. 1 prices
  • PMFMENothing for mushroom

    Read end to end against its primary document: it funds nothing for mushroom cultivation. That is a finding, not a gap.

    Verified against the primary government document.

  • AIFHelp on a loan, not a grant

    What this pays is an ongoing rate against loan repayments rather than a sum towards the build, so there is no single figure to show here. The rates are on its own page.

    Verified against the primary government document.

    See all 2 items AIF prices
  • NABARDNot read yet

    We have not yet read a primary document we can publish a rate against, so this atlas publishes none for it.

    Pending. We have not read a primary document for this yet. We do not publish unverified rates.

  • PMKSY Cold ChainNothing for mushroom

    Read end to end against its primary document: it funds nothing for mushroom cultivation. That is a finding, not a gap.

    Verified against the primary government document.

  • SMAM₹2.40 lakh

    At most, for its biggest single item: The same packing-machine financing, at the general-beneficiary rate.

    Private applicant, NE & Himalayan State, 40%.

    SMAM Operational Guidelines 2024Printed 2024Show evidence

    SUB-MISSION ON AGRICULTURAL MECHANIZATION (SMAM) OPERATIONAL GUIDELINES - 2024 (SMAM Operational Guidelines 2024)

    Ministry of Agriculture and Farmers Welfare, Department of Agriculture & Farmers Welfare, Government of India

    Printed 2024

    Covering letter (PDF p.1), verified against pg-01.png, verbatim: "F.No.3-4/2020-M&T(I&P) (81291), Government of India, Ministry of Agriculture & Farmers Welfare, (Department of Agriculture & Farmers welfare), (Mechanization & Technology Division), Krishi Bhawan, New Delhi,…Read the full clause
    Covering letter (PDF p.1), verified against pg-01.png, verbatim: "F.No.3-4/2020-M&T(I&P) (81291), Government of India, Ministry of Agriculture & Farmers Welfare, (Department of Agriculture & Farmers welfare), (Mechanization & Technology Division), Krishi Bhawan, New Delhi, Dated: 7th November, 2024 — Subject: Revision in the Operational Guidelines of Sub Mission on Agricultural Mechanization under the umbrella of Rashtriya Krishi Vikas Yojana... The guidelines have been revised by inclusion of provisions for financial assistance for the FRA Patta holders beneficiaries." Section 5.1 (PDF p.11), Table of Contents entry and body text both read "Demonstration of newly developed agricultural/ horticultural/ crop residue management machines post-harvest technologies...", explicit confirmation the scheme's scope spans horticulture, not just field-crop agriculture, even though no individual crop (mushroom included) is ever named. See the noMushroomComponent-style finding recorded on the scheme (below) and the per-rule clauses for where the actual computable rates come from (Annexure-I, not Section 5.1, which funds institutional demonstration grants, not individual farmer purchases).

    PDF p.1 (covering letter); p.2 (cover); p.11 (§5.1); p.6 (§4.1); p.20 onward (Annexure-I); p.33 (items q/r/t cited on the rules)

    Read on 11 September 2026 by chirag.

    Verified against the primary government document.

    See all 6 items SMAM prices
  • PM-RKVYNot read yet

    We have not yet read a primary document we can publish a rate against, so this atlas publishes none for it.

    Pending. We have not read a primary document for this yet. We do not publish unverified rates.

What to do next

Work out what your own project would draw.

What you actually draw in Tripura depends on what you build and what it costs. The calculator asks where you are, what you are building and what it costs, then prices every scheme on this site against that, shows the document behind each figure, and writes a link you can send to your bank.

Open the calculator

Or have MushroomWale build it.

MushroomWale designs and builds mushroom farms. For the farms we build, we also prepare and pursue the claim: the DPR, the documents, the bank, the sanctioning department and the joint inspection.

We prepare and pursue the claim only for farms we build.

Talk to MushroomWale about building it